OMB COST ESTIMATE
FOR PAY-AS-YOU-GO CALCULATIONS
Report No: 499
Date: 01/03/00
(Fiscal years; in millions of dollars) | ||||||
1999 | 2000 | 2001 | 2002 | 2003 | 2004 | |
Net costs..................... | 0 | 0 | 0 | 0 | 0 | 0 |
P.L. 106-144 directs the Secretary of Agriculture to convey up to 240 acres of federal land to the city of Sisters, Oregon. The law authorizes the city to pay for the land by waiving discretionary utility payments the city otherwise would receive from the Forest Service.
(Fiscal years; in millions of dollars) | ||||||
1999 | 2000 | 2001 | 2002 | 2003 | 2004 | |
Net costs.................... | 0 | 1 | 0 | 0 | 0 | 0 |
CBO estimates the city would make a cash payment for the land under current law, and therefore, scores the foregone cash receipts in 2000. OMB does not score any costs, because it does not assume such cash receipts in its baseline.
(Fiscal years; in millions of dollars) | ||||||
1999 | 2000 | 2001 | 2002 | 2003 | 2004 | |
Outlay effect.............. | 53 | 723 | 963 | 609 | 818 | -55 |
Receipt effect............ | -5 | 3,659 | 1,779 | 769 | 1,985 | 37 |
Net costs.................... | 58 | -2,936 | -816 | -160 | -1,167 | -92 |