June 19, 1998
MEMORANDUM FOR THE CHIEF OPERATING OFFICERS OF SELECTED DEPARTMENTS AND AGENCIES
FROM: | Ed DeSeve |
SUBJECT: | Progress Addressing the Year 2000 Computer Problem in Mission Critical Systems |
Schedule for Mission Critical Systems to be Compliant
Department/Agency |
Number of Systems 1/ |
7/98 |
8/98 |
9/98 |
10/98 |
11/98 |
12/99 |
1/99 |
2/99 |
3/99 |
Department’s Plan |
|
|
|
|
|
|
|
|
|
|
Current Estimate 2/ |
100 |
36 |
40 |
45 |
49 |
55 |
62 |
71 |
85 |
100 |
Actual |
|
|
|
|
|
|
|
|
|
|
Major Component A’s Plan |
|
|
|
|
|
|
|
|
|
|
Current Estimate 2/ |
32 |
12 |
13 |
15 |
19 |
25 |
31 |
32 |
32 |
32 |
Actual |
|
|
|
|
|
|
|
|
|
|
Major Component B’s Plan |
|
|
|
|
|
|
|
|
|
|
Current Estimate 2/ |
21 |
10 |
10 |
10 |
13 |
13 |
16 |
16 |
17 |
21 |
Actual |
|
|
|
|
|
|
|
|
|
|
1/ The number of systems is total number of mission critical systems minus those being retired.
2/ Also include previously reported estimates, if the current estimates have changed.
Schedule for Mission Critical Systems to be Renovated
Department/Agency |
Number of Systems 3/ |
7/98 |
8/98 |
9/98 |
Department’s Plan |
|
|
|
|
Current Estimate 4/ |
50 |
32 |
44 |
50 |
Actual |
|
|
|
|
Major Component A’s Plan |
|
|
|
|
Current Estimate 4/ |
18 |
10 |
13 |
18 |
Actual |
|
|
|
|
Major Component B’s Plan |
|
|
|
|
Current Estimate 4/ |
17 |
8 |
10 |
17 |
Actual |
|
|
|
|
3/ The number of systems is the number of mission critical system that are being or have been repaired.
4/ Also include previously reported estimates, if the current estimates have changed.
Schedule for Mission Critical Systems to be Validated
Department/Agency |
Number of Systems 5/ |
7/98 |
8/98 |
9/98 |
10/98 |
11/98 |
12/98 |
1/98 |
Department’s Plan |
|
|
|
|
|
|
|
|
Current Estimate 6/ |
50 |
17 |
19 |
24 |
29 |
34 |
40 |
50 |
Actual |
|
|
|
|
|
|
|
|
Major Component A’s Plan |
|
|
|
|
|
|
|
|
Current Estimate 6/ |
18 |
8 |
8 |
9 |
11 |
12 |
15 |
18 |
Actual |
|
|
|
|
|
|
|
|
Major Component B’s Plan |
|
|
|
|
|
|
|
|
Current Estimate 6/ |
17 |
5 |
6 |
8 |
10 |
12 |
13 |
17 |
Actual |
|
|
|
|
|
|
|
|
5/ The number of systems is the number of mission critical system that are being or have been repaired.
6/
Schedule for Mission Critical Systems to be Implemented
Department/Agency |
Number of Systems 7/ |
7/98 |
8/98 |
9/98 |
10/98 |
11/98 |
12/99 |
1/99 |
2/99 |
3/99 |
Department’s Plan |
|
|
|
|
|
|
|
|
|
|
Current Estimate 8/ |
50 |
7 |
9 |
12 |
16 |
20 |
26 |
34 |
41 |
50 |
Actual |
|
|
|
|
|
|
|
|
|
|
Major Component A’s Plan |
|
|
|
|
|
|
|
|
|
|
Current Estimate 8/ |
18 |
3 |
3 |
3 |
6 |
6 |
7 |
7 |
12 |
18 |
Actual |
|
|
|
|
|
|
|
|
|
|
Major Component B’s Plan |
|
|
|
|
|
|
|
|
|
|
Current Estimate 8/ |
17 |
2 |
2 |
4 |
5 |
6 |
8 |
11 |
12 |
17 |
Actual |
|
|
|
|
|
|
|
|
|
|
8/ Also include previously reported estimates, if the current estimates have changed.